After finishing the over rotation-speed testing of the turbine, the unit 1 of Qinshan Phase II NPP connected the grid successfully at 21:48 of Apr. 12. According to the schedule, this unit will put into full power operation in Apr. 16.
Since disconnected from the grid at 02:35 of Mar. 11, this outage has lasted 32 days plus 19 hours more than 7 days ahead the planning date. A significant promotion of core fuel management strategy was implemented in core fuel loading of this outage.
|